File #: ID-1890-20    Name:
Type: Change Orders/Pay Estimates /Final Payments Status: Agenda Ready
File created: 10/28/2024 In control: Public Service Committee
On agenda: 11/4/2024 Final action:
Title: Change Order No. 1 for the Combined Sewer Overflow Long Term Control Plan Phase IV- Eastside and Westside Combined Sewer Overflow Regulators to D Construction Inc. in the amount of $168,441.10
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 1 for the Combined Sewer Overflow Long Term Control Plan Phase IV- Eastside and Westside Combined Sewer Overflow Regulators to D Construction Inc. in the amount of $168,441.10

end

 

BACKGROUND:

On June 6, 2023, the Mayor and City Council awarded a Contract for the Combined Sewer Overflow Long Term Control Plan Phase IV- Eastside and Westside Combined Sewer Overflow Regulators, in the amount of $12,628,985.00, to D Construction Inc. 

 

The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 1, a net increase in the amount of $168,441.10, is for the following work:

 

                     Provide a mooring point to replace the existing mooring point in accordance with United States Army Corps of Engineers comments provided after the bids were received.

                     Provide nine surface mounted guard posts around the Combined Sewer Regulator Structure at CSO site 011 in lieu of three buried guard posts.

                     Increase the size of the 15-inch throttle pipe at CSO site 009 to 27-inches due to the upcoming Interstate 80 project and provide an additional manhole structure.

                     Time and material work for watermain and sanitary work that were not on the plans at CSO 011.

                     Time and material work for repairs to an unknown watermain at CSO 009 site.

 

Funds will be charged to the Long Term Control Plan Phase IV Fund / Construction (Org 53080000, Object 557200, $168,441.10).

 

The City of Joliet will be reimbursed for $105,496.00 of the proposed Change Order No. 1 by the Illinois Department of Transportation.  The work was required due to the I-80 bridge relocation and will be included on a future Intergovernmental Agreement with IDOT.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1, a net increase in the amount of $168,441.10 to the Combined Sewer Overflow Long Term Control Plan Phase IV- Eastside and Westside Combined Sewer Overflow Regulators, on behalf of D Construction, Inc.