TO: Mayor and City Council
FROM: Beth Beatty, City Manager
SUBJECT:
title
Change Order No. 4 for the Joliet Ottawa Water Main Improvements Project to Trine Construction Corp in the amount of $229,372.25
end
BACKGROUND:
On January 17, 2023, the Mayor and City Council awarded a Contract for the Joliet Ottawa Water Main Improvements Project, in the amount of $6,095,346.00, on behalf of Trine Construction Corp., based on the Unit Prices provided in their bid. Subsequently, Change Orders Nos. 1-3 were approved for a net increase of $309,055.32. The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 4, a net addition in the amount of $229,372.25 is for the following work:
• Additional trench backfill (special)
• Additional rock excavation
• Additional water main (open) cut, 6-inch
• Additional sanitary sewer removal and replacement, 8-inch
• Additional storm sewer removal and replacement, 8-inch
Sufficient funds are available for this project in the Water Main Replacement Fund (Org 53880000, Object 557200, $229,372.25).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 4 to the contract for the Joliet Ottawa Water Main Improvements Project, in the amount of $229,372.25, on behalf of Trine Construction Corp.
end