Change Order No. 1 for the Bridge Street (Nicholson Street - N. Center Street) Roadway Improvement Project - MFT Section No. 24-00562-00-FP to PT Ferro Construction Co. in the Amount of $18,500.00
end
BACKGROUND:
On April 16, 2024, the Mayor and City Council awarded a contract for the Bridge Street (Nicholson Street - N. Center Street) Roadway Improvement Project - 2024, in the amount of $358,405.93 to PT Ferro Construction Co.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1, a net increase in the amount of $18,500.00, is the result of the following items:
1. Addition of 4” asphalt binder course patching necessary due to utility delays.
2. Addition of 3” asphalt surface course patching necessary due to utility delays.
Funds will be charged to Motor Fuel Tax Fund / Roadway Reconstruction Bridge (Org 20090270, Object 557200, Project 24024 $18,500.00).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 in the amount of $18,500.00 on behalf of PT Ferro Construction Co.