Title: Change Order No. 3 for the Broadway Street (West Marion Street - West Jefferson Street) Roadway Reconstruction Project - MFT Section No. 23-00557-00-FP to PT Ferro Construction Co. for a Decrease in the Amount of ($17,226.37) and Payment Estimate No. 6 and Final in the Amount of $53,479.75
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Greg Ruddy, Director of Public Works

 

SUBJECT:

title

Change Order No. 3 for the Broadway Street (West Marion Street - West Jefferson Street) Roadway Reconstruction Project - MFT Section No. 23-00557-00-FP to PT Ferro Construction Co. for a Decrease in the Amount of ($17,226.37) and Payment Estimate No. 6 and Final in the Amount of $53,479.75

end

 

BACKGROUND:

On Tuesday, February 6, 2024, the Mayor and City Council awarded the Broadway Street (West Marion Street - West Jefferson Street) Roadway Reconstruction Project - MFT Section No. 23-00557-00-FP, in the amount of $1,247,095.87, to PT Ferro Construction Co.  Subsequently, Change Orders No. 1 and 2 were approved by the Mayor and City Council.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the City.  Change Order No. 3, a net reduction in the amount ($17,226.37) is the result of the following:

 

1.                     Encountering less unsuitable material than anticipated.

 

2.                     Replacing public sidewalk due to water main installation.

 

Funds are available using Water & Sewer funds / Watermain replacement (Org 50180012, Object 557200, $29,472.00) and Property Owner Improvement Funds (Org 10090000, Object 524300, $1,615.00).

 

Change Order No. 3 reflects a reduction in contribution from the MFT Fund (Org 20090270, Object 557200, ($48,163.37)) and the Special Service Area Fund (Org 23020240, Object 557200, ($150.00)).

 

Also, included is Payment Estimate No. 6 and Final, in the amount of $53,479.75, on behalf of PT Ferro Construction Co.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 3, a net deduction in the amount of ($17,226.37).

 

2.                     Approve Payment Estimate No. 6 and Final in the amount of $53,479.75 on behalf of PT Ferro Construction Co.