TO: Mayor and City Council
FROM: Beth Beatty, City Manager
SUBJECT:
title
Change Order No. 1 for the Fairmont Water Tower Demolition Project to Green Demolition Services in the amount of $18,200.00
end
BACKGROUND:
On Tuesday, November 21, 2023, the Mayor and City Council awarded a contract to Green Demolition Contractors Inc., in the amount of $48,500.00, for the demolition of the Fairmont Water Tower. The scope of work only included demolition of the water tower and did not include demolition of the fence or concrete bases. The fence has become overgrown with vegetation leaving the site in poor condition. Since Green Demolition Contractors Inc. is mobilizing equipment to the Fairmont site, Staff contacted the contractor to provide a price to remove everything on site including the fence and concrete bases and to restore the site with grass when complete.
The Public Service Committee will review this matter.
CONCLUSION:
Green Demolition Contractors Inc. provided a proposal in the amount of $18,200.00 to remove everything on site including the fence and concrete bases and to restore the site with grass when complete.
Funds will be charged to the Water and Sewer Improvement Fund / Projects / Construction (Org 50180011, Object 557200, $18,200.00, Project 23043).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1, a net increase in the amount of $18,200.00, for the Fairmont Water Tower Demolition project.
end