TO: Mayor and City Council
FROM: Beth Beatty, City Manager
SUBJECT:
title
Change Order No. 1 for the Ottawa Street / Joliet Street Streetscape Project to PT Ferro Construction Co. in the Amount of $10,460.07
end
BACKGROUND:
On September 3, 2024, the Ottawa Street / Joliet Street Streetscape Repair Project was awarded by the Mayor and City Council in the amount or $113,238.36.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1, a net increase of $10,460.07, is the result of replacing additional sidewalk along Ottawa Street in front of the Joliet Public Library.
Sufficient funds exist utilizing the Public Works Capital Improvement Fund / Infrastructure (Org 30090270, Object 557200, $10,406.07) due to other roadway projects coming in under budget.
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 in the amount of $10,460.07 on behalf of PT Ferro Construction Co.
end