Title: Award of Contract for the Plainfield Road (Theodore Street - Black Road) Water Main Improvements Project to Austin Tyler Construction Inc. in the amount of $9,475,973.24
Attachments: 1. Approver Report
TO: Mayor and City Council

FROM: Beth Beatty, City Manager

SUBJECT:
title
Award of Contract for the Plainfield Road (Theodore Street - Black Road) Water Main Improvements Project to Austin Tyler Construction Inc. in the amount of $9,475,973.24
end

BACKGROUND:
On January 5, 2021, the Mayor and City Council approved Resolution No. 7613, committing to water conservation through the reduction of non-revenue water in order to comply with the allocation requirements of the Level of Lake Michigan Act, 615 ILCS 50, and the corresponding State regulations. A condition of the City's Lake Michigan water allocation permit is completion of the City's Non-Revenue Water Reduction Plan. A major component of this Plan is water main replacement. The water main replacement, estimated at approximately 3% per year, must be sufficient to achieve the reduction of non-revenue water from the City's water system to not more than 10 percent by the year 2030.

The 2024 Water Main Replacement Program consists of 18 contracts to replace a total of approximately 33 miles of water main, at an as-bid cost of approximately $83,500,000. The Plainfield Road (Theodore Street - Black Road) Water Main Improvements Project was identified to be completed as part of this program. The project consists of replacing approximately 10,100 linear feet of water main in various sizes on Plainfield Road (Theodore Street to Black Road). Also included in this project is sanitary sewer work consisting of replacing approximately 900 LF of sanitary sewer from a 10-inch pipe to a 15-inch pipe to increase capacity to help reduce the frequency of basement backups in the Kerwin Estates area. Included in this memo is an exhibit showing the project location.

Also included in the scope of this construction project is lead water service line replacements. If lead water services are encountered during the project, they will be replaced, and these costs will be charged to the Phase V lead water service line rep...