Legislation Details

File #: ID-1580-20   
Type: Contracts Status: Agenda Ready
File created: 1/30/2024 In control: Public Service Committee
On agenda: 2/5/2024 Final action:
Title: Professional Service Agreement for the Construction Testing / Soil Boring Services for the 2025 Water Main Improvement Program to K & S Engineers Inc. in the amount of $99,885.00
Attachments: 1. BoreLocation_Binder1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and City Council

FROM: Beth Beatty, City Manager

SUBJECT:
title
Professional Service Agreement for the Construction Testing / Soil Boring Services for the 2025 Water Main Improvement Program to K & S Engineers Inc. in the amount of $99,885.00
end

BACKGROUND:
On January 5, 2021, the Mayor and City Council approved Resolution No. 7613, committing to water conservation through the reduction of non-revenue water in order to comply with the allocation requirements of the Level of Lake Michigan Act, 615 ILCS 50, and the corresponding State regulations. A condition of the City's Lake Michigan water allocation permit is completion of the City's Non-Revenue Water Reduction Plan. A major component of this Plan is water main replacement. The water main replacement, estimated at approximately 3% per year, must be sufficient to achieve the reduction of non-revenue water from the City's water system to not more than 10 percent by the year 2030.

The design of the 2025 Water Main Replacement Program is underway, and geotechnical information for the project areas is needed for the design. The scope of this needed geotechnical work includes soil borings, soil screenings, laboratory testing, geotechnical evaluation, and environmental testing. This work scope also includes research to identify locations where excavated soils can be disposed of at a standard disposal site and to identify locations where excavated soils need to be disposed of at a special waste site.

Proposals were requested from three qualified firms on Friday, January 19, 2024. The Public Service Committee will review this matter.

CONCLUSION:
On Friday, January 26, 2024, at 10:00 a.m., two proposals were received for the Construction Testing / Soil Boring Services for the 2025 Water Main Improvement Program. The proposal summary is as follows:

CONTRACTOR AMOUNT
K & S Engineers Inc., Highland, IN $99,885.00
Seeco Consultants Inc., Tinley Park, IL $119,707.00
Testing...

Click here for full text