Legislation Details

File #: 243-24   
Type: Consent Agenda Status: Passed
File created: 5/9/2024 In control: City Council Meeting
On agenda: 5/21/2024 Final action: 5/21/2024
Title: Change Order No. 3 for the Joliet Ottawa Water Main Improvements Project on behalf of Trine Construction Corp in the amount of $191,787.91
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 3 for the Joliet Ottawa Water Main Improvements Project on behalf of Trine Construction Corp in the amount of $191,787.91

end

 

BACKGROUND:

On January 17, 2023, the Mayor and City Council awarded a Contract for the Joliet Ottawa Water Main Improvements Project, in the amount of $6,095,346.00, on behalf of Trine Construction Corp based on the Unit Prices provided in their bid.  Subsequently, Change Orders Nos. 1 & 2 were approved for a net increase of $117,267.41.  The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 3, a net addition in the amount of $191,787.91 is for the following work:

 

•                     Additional rock excavation

•                     Additional water main (open) cut, 24-inch

•                     Additional gate valve, 6-inch

•                     Additional valve box

•                     Additional temporary hot mix asphalt pavement

•                     Additional exploratory excavation

 

Sufficient funds are available for this project in the Water & Sewer Improvement Fund / Water Distribution (Org 53880000, Object 557200, $191,787.91).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 3 to the contract for the Joliet Ottawa Water Main Improvements Project, in the amount of $191,787.91, on behalf of Trine Construction Corp.