Legislation Details

File #: ID-1860-20   
Type: Ordinances and Resolutions Status: Agenda Ready
File created: 9/20/2024 In control: Public Service Committee
On agenda: 9/30/2024 Final action:
Title: Resolution Approving an Agreement with the Illinois Department of Transportation for Construction and Phase III Engineering Services for the Theodore Street (Drauden Road - Wesmere Parkway) Roadway Widening Improvements Project - MFT Section No. 18-00515-01-WR
Attachments: 1. Resolution, 2. LPA AGREEMENT C-91-277-24.pdf
TO: Mayor and City Council

FROM: Beth Beatty, City Manager

SUBJECT:
title
Resolution Approving an Agreement with the Illinois Department of Transportation for Construction and Phase III Engineering Services for the Theodore Street (Drauden Road - Wesmere Parkway) Roadway Widening Improvements Project - MFT Section No. 18-00515-01-WR
end

BACKGROUND:
The City is working towards improving Theodore Street between Drauden Road and IL Route 59 with construction being completed in phases. Project 1a, located between Wesmere Parkway and River Road, is currently under construction. Project 1b, with limits between Drauden Road and Wesmere Parkway, is being prepared for an IDOT Letting on November 8, 2024.

The City has been approved for Federal funding through the Surface Transportation Program (STP) to complete roadway widening improvements for Project 1b. The improvements consist of the widening of Theodore Street to a five-lane cross section, installation of a traffic signal at the intersection of Theodore Street and Drauden Road and the installation of a bike path.

The total estimated cost of the Construction and Construction Engineering (Phase III Engineering) is in the amount of $3,895,666.00, with a federal share of $3,116,533.00 (STP funds) and a City share of $779,133.00 (MFT Funds).

The Public Service Committee will review this matter.

CONCLUSION:
Attached is a Resolution approving a Joint Funding Agreement for Federally Funded Construction (Agreement) with the Illinois Department of Transportation for the subject project. The cost estimate for Construction is in the amount of $3,541,666.00. The cost estimate for Construction Engineering (Phase III Engineering) is in the amount of $354,000.00. These costs will be split on an 80% federal / 20% local basis. As part of the Agreement with IDOT, the City is responsible to hire a consulting engineer for the Construction Engineering services. The City of Joliet is responsible to initially provide full ...

Click here for full text