Title: Change Order No. 1 for the Parkview North Water Main Improvements Project to PT Ferro Construction Co. in the amount of $66,320.00
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 1 for the Parkview North Water Main Improvements Project to PT Ferro Construction Co. in the amount of $66,320.00

end

 

BACKGROUND:

On January 16, 2024, the Mayor and City Council awarded a Contract for the Parkview North Water Main Improvements Project, in the amount of $7,588,214.54, on behalf of PT Ferro Construction Co., based on the Unit Prices provided in their bid.  The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 1, a net addition in the amount of $66,320.00, is for the following work which was a result of unforeseen conditions and additions for improved system functionality:

 

•                     Additional water main (open cut), 12-inch

•                     Additional water main (in jacked casing), 8-inch in 36-inch casing

•                     Additional connect to water main (non-pressure), 6-inch

•                     Additional gate valve, 6-inch

•                     Additional butterfly valve, 16-inch

•                     Additional valve box

 

Sufficient funds are available for this project in the Watermain Replacement Fund (Org 53880000, Object 557200, $66,320.00).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 to the contract for the Parkview North Water Main Improvements Project, in the amount of $66,320.00, on behalf of PT Ferro Construction Co.