Legislation Details

File #: 93-25   
Type: Agenda Item Status: Passed
File created: 1/24/2025 In control: City Council Meeting
On agenda: 2/4/2025 Final action: 2/4/2025
Title: Award of Professional Services Agreement for Construction Related Engineering Services for the 2025 Water Main and Lead Water Service Line Replacement Programs to Burns & McDonnell Engineering Company, Inc. in the Amount of $4,584,963.79
Attachments: 1. 2025 WMRP - B&M CRS Proposal and Contract - revised.pdf, 2. 2025 WM Project Locations.pdf, 3. Approver Report
TO: Mayor and City Council

FROM: Allison Swisher, Director of Public Utilities

SUBJECT:
title
Award of Professional Services Agreement for Construction Related Engineering Services for the 2025 Water Main and Lead Water Service Line Replacement Programs to Burns & McDonnell Engineering Company, Inc. in the Amount of $4,584,963.79
end

BACKGROUND:
On January 5, 2021, the Mayor and City Council approved Resolution No. 7613, committing to water conservation through the reduction of non-revenue water in order to comply with the allocation requirements of the Level of Lake Michigan Act, 615 ILCS 50, and the corresponding State regulations. A condition of the City's Lake Michigan water allocation permit is completion of the City's Non-Revenue Water Reduction Plan. A major component of this Plan is water main replacement. The water main replacement, estimated at approximately 3% per year, must be sufficient to achieve the reduction of non-revenue water from the City's water system to not more than 10 percent by the year 2030.

The 2025 Water Main Replacement Program consists of 16 contracts to replace a total of approximately 29 miles of water main, at an estimated cost of $74,500,000.00. The scope of work for these contracts also includes:

1. Lead water service line replacements. Any lead water service lines encountered during water main construction will be replaced and these costs will be charged to the 2025 Lead Service Line Replacement Fund for which the City has secured State Revolving Fund financing with principal forgiveness. In addition to replacing any lead services encountered in the 2025 water main replacement projects, the City also bid a separate lead service line replacement project that will replace approximately 40 lead service lines encountered in locations outside of the water main replacement work.

2. Sanitary sewer repairs. Sanitary sewers with known defects will be repaired on the streets where water main work is being completed. ...