TO: Mayor and City Council
FROM: Greg Ruddy, Director of Public Works
SUBJECT:
title
Amendment No. 1 for the Phase II Engineering Services for the Farrell Road over Spring Creek Bridge Improvement Project - MFT Section No. 21-00542-00-BR to Hutchison Engineering Inc. in the Amount of $26,190.00
end
BACKGROUND:
On Tuesday, October 3, 2023, the Mayor and City Council awarded the Phase II Engineering Services contract for the Farrell Road over Spring Creek Bridge Improvement Project to Hutchison Engineering Inc. in the amount of $122,475.00. The scope of work included updating Phase I Engineering to current design standards and completion of Phase II Engineering.
The Public Service Committee will review this matter.
CONCLUSION:
Amendment No. 1, an addition in the amount of $26,190.00, is for extension of Engineering Services into spring of 2025 to complete the remaining work required for Phase II Engineering.
Sufficient funds are available in the Motor Fuel Tax Fund / Farrell Road Bridge (Org 20090270, Object 557200, $26,190.00).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Amendment No 1, an addition in the amount of $26,190.00, for the Phase II Engineering Services for the Farrell Rd over Spring Creek Bridge Improvement Project - MFT Section No. 21-00542-00-BR, on behalf of Hutchison Engineering Inc.
end