TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 1 for the Well 24D Rehabilitation Project to Water Well Solutions in the Amount of $36,224.24
end
BACKGROUND:
On Tuesday, February 3, 2026, the Mayor and City Council awarded a contract to Water Well Solutions in the amount of $211,949.00 for the rehabilitation of Well 24D. The scope of the project included removal, evaluation and reinstallation of the pump.
Water Well Solutions completed the removal of the pumping equipment and took it to their shop for evaluation. Upon disassembly of the pump it was determined that the pump was able to be rebuilt for reuse. Additional work was also identified and completed which included: lowering the pump 100 feet to allow for more coverage over the pump during operation, additional cable, additional transducer carrier pipe, and additional replacement pump components.
Also included with this change order is the abandonment of the Southeast Joliet Sanitary District (SEJSD) well. When the City took over operation of the former SEJSD water system, it was discovered that the District’s well was inoperable due to catastrophic failure. IEPA requires all wells to either be repaired and sampled monthly or abandoned by sealing the well. The well is not necessary for the operation of the SEJSD system as the system is being fed from the City’s existing wells. Therefore, the City requested permission from the IEPA to abandon the well to avoid violations for not repairing the well. Since Water Well Solutions worked on the well in the past and had detailed records about the well, Staff requested Water Well Solutions to seal the well on a time and material basis to satisfy IEPA’s requirement of abandoning the well.
The Public Service Committee will review this matter.
CONCLUSION:
The cost for Water Well Solutions to complete the Well 24D pump rebuild and other related work was $16,224.24, and the cost...