File #: 115-26   
Type: Consent Agenda Status: Agenda Ready
File created: 2/2/2026 In control: City Council Meeting
On agenda: 2/17/2026 Final action:
Title: Approval of Change Order No. 1 for the Construction of the Essington Road Bridge over Rock Run Creek Improvement Project - MFT Section No. 16-00489-00-BR to the Illinois Department of Transportation in the Amount of $112,158.64 and Payment No. 2 and Final in the Amount of $114,774.28
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Greg Ruddy, Director of Public Works

 

SUBJECT:

title

Approval of Change Order No. 1 for the Construction of the Essington Road Bridge over Rock Run Creek Improvement Project - MFT Section No. 16-00489-00-BR to the Illinois Department of Transportation in the Amount of $112,158.64 and Payment No. 2 and Final in the Amount of $114,774.28

end

 

BACKGROUND:

On December 17, 2019, the Mayor and City Council passed a Resolution approving an intergovernmental agreement with the Illinois Department of Transportation for the Construction of and Construction Engineering for the Essington Road Bridge over Rock Run Creek Improvement Project.  This agreement provided that the City would reimburse the Illinois Department of Transportation (IDOT) for 20% of the construction costs.  At the time the agreement was approved, the estimated City share of construction costs was $600,000.00.  This project has been satisfactorily completed, and the final City share is $562,158.64.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 1 is a net increase in the amount of $112,158.64.  The original purchase order established for this contract did not allocate the total funding required to cover the final cost of the project.  Change Order No. 1 will allow for payment of the final invoice from IDOT, and overall close-out of this project.

 

Sufficient funds are available in the Motor Fuel Tax Fund / Essington Rd. Bridge over Rock Run Creek Construction (Org 20090270, Object 557200, $112,158.64).

 

Also, please process Pay Estimate No. 2 & Final, in the amount of $114,744.28 on behalf of IDOT.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 1, an increase in the amount of $112,158.64, for the Construction for the Essington Road Bridge over Rock Run Creek Improvement Project - MFT Section No. 16-00489-00-BR.

 

2.                     Approve Pay Estimate No. 2 and Final, in the amount of $114,744.28, on behalf of IDOT.