Legislation Details

File #: 438-26   
Type: Agenda Item Status: Passed
File created: 8/19/2026 In control: City Council Meeting
On agenda: 9/1/2026 Final action: 9/1/2026
Title: Approval of Change Order No. 1 for the Upper Bluff Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($551,910.46) and Pay Estimate No. 7 and Final in the Amount of $869,608.13
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the Upper Bluff Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($551,910.46) and Pay Estimate No. 7 and Final in the Amount of $869,608.13

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the Upper Bluff Water Main Improvements, in the amount of $5,685,247.00, on behalf of Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 1, a net decrease in the amount of ($551,910.46), is a final balancing change order for the following work:

•                     Balancing of final quantities

•                     Deduction for unused quantities

•                     Time extension due to winter conditions

•                     Dixon Street ground augers

•                     Unmarked water service at 605 Buell

•                     Water main repair at 615 Buell

•                     Expose valve and install flushing whips at Dixon Street

•                     Unmarked water service at Brooks Street

•                     Abandon existing unknown tunnel in alley

•                     Repair and re-route sewer service at 507 Jersey

•                     Water main repair at Western & Clement

•                     Water main repair at Western & Clement # 2

•                     Remove and repair sewer at Division Street

•                     Remove abandoned 6" gas main at Division Street on 9/27

•                     Remove abandoned 6" gas main at Division Street on 9/29

•                     Repair water services on Carson Ave

•                     24" sewer repair due to abandoned 6" stub in water trench at Buell

•                     Re-establish grade for HDD due to sanitary depth at Division & Nicholson

•                     Mismarked water service on Buell and Woodworth

•                     Repair and re-route sewer service on Whitney

•                     Provide valve box extension at 409 Whitney

•                     Re-grade alley between Nicholson & Woodworth after main install

 

Funds will be credited to the Water Main Replacement Fund (Org 53880000, Object 557200, ($659,752.46)) and charged to the Water & Sewer Improvement Fund / Sewer Collection / Construction (Org 50180020, Object 557200, $107,842.00, Project 25008).

 

Also, Pay Estimate No. 7 and Final in the amount of $869,608.13 is provided for approval.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No.1, for a decreased amount of ($551,910.46), to the contract for the Upper Bluff Water Main Improvements Project.

 

2.                     Approve Pay Estimate No. 7 and Final, in the amount of $869,608.13, on behalf of Austin Tyler Construction Inc.

end