Legislation Details

File #: 592-26   
Type: Consent Agenda Status: Agenda Ready
File created: 11/18/2026 In control: City Council Meeting
On agenda: 12/1/2026 Final action:
Title: Approval of Change Order No. 1 for the Cunningham Phase 1 Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($483,877.29)
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the Cunningham Phase 1 Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($483,877.29)

end

 

BACKGROUND:

On January 20, 2026, the Mayor and City Council awarded a Contract for the Cunningham Phase 1 Water Main Improvements Project, in the amount of $4,256,274.71, on behalf of Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 1 is a final balancing change order with a net decrease, in the amount of ($483,877.29), for the following work:

•                     Balancing of final quantities

•                     Deduction for unused quantities

•                     Connect to existing water main (non-pressure), 6-inch

•                     Specialty landscaping restoration at 925 Oakland

•                     Repair unknown 4" water main at Raynor & Ross

•                     Repair sanitary service lateral at Kelly & Moran

•                     Modification of service line to CVS pharmacy

•                     Gas removal in conflict with water main installation

•                     Repair sanitary service lateral at 914 Wilcox

•                     Unknown water main at Ross & Oakland

•                     Repair sanitary service lateral at 916 Raynor

•                     Remobilize to install additional water services

•                     Locate mismarked water service at 808 Vine Street

•                     Locate service line for Cunningham School

•                     Locate service line for 910 Clement

•                     Repair sanitary service lateral at 551 Ross

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($480,421.44)) and the Water & Sewer Improvement Fund / Sewer Collection (Org 50180020, Object 557200, ($3,455.85)).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1, for a decreased amount of ($483,877.29), for the Cunningham Phase 1 Water Main Improvements Project, on behalf of Austin Tyler Construction Inc.

end