File #: 168-26   
Type: Agenda Item Status: Passed
File created: 3/4/2026 In control: City Council Meeting
On agenda: 3/16/2026 Final action: 3/16/2026
Title: Approval of Change Order No. 1 for the Emerald Lawns Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the amount of ($571,601.18) and Pay Estimate No. 6 and Final in the amount of $614,195.92
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the Emerald Lawns Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the amount of ($571,601.18) and Pay Estimate No. 6 and Final in the amount of $614,195.92

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the Emerald Lawns Water Main Improvements Project, in the amount of $5,682,093.90, on behalf of Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 1, a net decrease in the amount of ($571,601.18), is a final balancing change order for the following work:

•                     Time extension to contract milestones due to weather delays and delays due to testing

•                     Additional Water Main (Open Cut), 8-Inch

•                     Additional Water Main (Open Cut), 12-Inch

•                     Additional Connect to Water Main (Non-Pressure), 8-Inch

•                     Additional Gate Valve, 12-Inch

•                     Additional Valve Vault, 5-Foot Diameter

•                     Additional Storm Sewer Remove & Replace, 12-Inch

•                     Additional Water Service Connect to Main & Curb Stop, 1-Inch

•                     Additional Water Service Line Type K - Directional Drill, 1-Inch

•                     Additional Restoration of Lawns & Parkways

•                     Additional HMA Remove & Replace, 2.5-Inch Binder 1.5-Inch Surface

•                     Additional HMA Remove & Replace, 4.5-Inch Binder 1.5-Inch Surface

•                     Additional Detectable Warnings

•                     Additional Pavement Marking - Letters & Symbols

•                     Additional Water Service Line Type L (LSR), 3/4-Inch

•                     Extra work due to abandoned gas main removal & water service repair

•                     Extra work due to unmarked 2-in water service

•                     Extra work due to delay from a water main break

•                     Extra work for unmarked service at 1217 Clara

•                     Deduction of unused quantities

•                     Deduction for unused lead service line replacement pay items

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($571,601.18)).

 

Also, please process Pay Estimate No. 6 and Final, in the amount of $614,195.92, on behalf of Austin Tyler Construction Inc.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No.1, for a decreased amount of ($571,601.18), for the Emerald Lawns Water Main Improvements Project.

 

2.                     Approve Pay Estimate No. 6 and Final, in the amount of $614,195.92, on behalf of Austin Tyler Construction Inc.