Title: Approval of Change Order No. 1 for the Highland Phase 2 Water Main Improvements Project to Airy's Inc. for a Deduction in the Amount of ($191,793.40) and Pay Estimate No. 4 and Final in the Amount of $1,388,541.22
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the Highland Phase 2 Water Main Improvements Project to Airy’s Inc. for a Deduction in the Amount of ($191,793.40) and Pay Estimate No. 4 and Final in the Amount of $1,388,541.22

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the Highland Phase 2 Water Main Improvements Project, in the amount of $2,649,317.00, on behalf of Airy’s Inc., based on the Unit Prices provided in their bid.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 1 is a final balancing change order with a net decrease in the amount of ($191,793.40) for the following work:

 

                     Balancing of final quantities

                     Deduction for unused quantities

                     Additional Water Main (Open Cut), 8-Inch

                     Additional Gate Valve, 8-Inch

                     Additional Valve Vault, 4-Foot Diameter

                     Additional Valve Vault (Additional Depth), 4-Foot Diameter

                     Additional Water Service Connection to Water Main and Curb Stop, 1.5-Inch

                     Additional Water Service Connection to Water Main and Curb Stop, 2-Inch

                     Additional Water Service Line Type K - Directional Drilling, 1-Inch

                     Additional Water Service Line Type K - Directional Drilling, 1.5-Inch

                     Additional Water Service Line Type K - Directional Drilling, 2-Inch

                     Additional Restoration of Lawns and Parkways

                     Additional Hot-Mix Asphalt Removal and Replacement, 2.5-Inch Binder 1.5-Inch Surface

                     Additional PCC Sidewalk Removal and Replacement

                     Additional Pavement Marking - Line, 6-Inch (Thermoplastic)

                     Connection to Water Main (Pressure), 8-Inch

                     Deduction in PCC and HMA Restoration Quantities

                     Deduct Water Main (Open Cut), 6-Inch, Di

                     Deduct Water Main (Open Cut), 8-Inch, Di

                     Deduct Connect to Water Main (Non-Pressure), 12-Inch

                     Deduct Fire Hydrant Barrel Extension

                     Deduct Line Stop, 8-Inch

                     Deduct Line Stop, 12-Inch

                     Deduct Remove and Replace Drain Tiles, 6-Inch Through 12-Inch

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($191,793.40)).

 

A time extension of 63 days due to an authorized delay in the project start date is also included with this change order.

 

Also, Pay Estimate No. 4 and Final is provided for approval, in the amount of $1,338,541.22, on behalf of Airy’s Inc.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No.1, for a decreased amount of ($191,793.40), to the Highland Phase 2 Water Main Improvements Project.

 

2.                     Approve Pay Estimate No. 4 and Final, in the amount of $1,338,541.22, on behalf of Airy’s Inc.