Legislation Details

File #: 488-26   
Type: Consent Agenda Status: Agenda Ready
File created: 9/24/2026 In control: City Council Meeting
On agenda: 10/6/2026 Final action:
Title: Approval of Change Order No. 2 for the Midland & Campbell Water Main Improvements Project on behalf of Len Cox & Sons Excavating for a Deduction in the Amount of ($599,165.12)
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 2 for the Midland & Campbell Water Main Improvements Project on behalf of Len Cox & Sons Excavating for a Deduction in the Amount of ($599,165.12)

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the Midland & Campbell Water Main Improvements Project, in the amount of $3,923,952.36, on behalf of Len Cox & Sons Excavating, based on the unit prices provided in their bid.  Subsequently, Change Order No. 1, a zero cost, time extension change order was approved.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 2 is a final balancing change order with a net decrease in the amount of ($599,165.12) for the following work:

•                     Balancing of final quantities

•                     Deduction for unused quantities

•                     Catch Basin Reconstruction

•                     Valve Vault Connection

•                     Remove abandoned structure

•                     Water main modifications due to existing conditions

•                     Existing vault removal

•                     Valve installation at the existing water main

•                     Additional excavation at Jewel entrance

•                     Modification of the proposed water main due to existing phone duct

•                     Modify water main alignment and re-excavate

•                     Water main repair 1301 Campbell

•                     Sewer conflict at Prairie & Campbell

•                     Water Main Modifications at Prairie & Campbell

•                     Exploratory excavation of existing 16" & 20" water mains

•                     Downtime due to poor shut down at William Street

•                     Downtime due to water taps scheduling delay

•                     Unlocatable service line at Pershing school

 

Funds will be decreased as follows for this project: Water Main Replacement Fund / Construction (Org 53880000, Object 557200, ($488,230.12)), Lead Water Service Line Replacement / Construction (Org 5388000, Object 557200, ($107,935.00)) and Sanitary Sewer Infrastructure (Org 50180020, Object 557200, ($3,000.00)).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 2 for a decreased amount of ($599,165.12) to the contract for the Midland & Campbell Water Main Improvements Project on behalf of Len Cox & Sons Excavating.