File #: 200-25   
Type: Consent Agenda Status: Passed
File created: 3/4/2025 In control: City Council Meeting
On agenda: 3/18/2025 Final action: 3/18/2025
Title: Change Order No. 2 for the Collins Street Water Main Improvements Project to Austin Tyler Construction, Inc. for a Decreased Amount of ($523,574.56) and Pay Estimate No. 8 and Final in the Amount of $1,024,211.90
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Change Order No. 2 for the Collins Street Water Main Improvements Project to Austin Tyler Construction, Inc. for a Decreased Amount of ($523,574.56) and Pay Estimate No. 8 and Final in the Amount of $1,024,211.90

end

 

BACKGROUND:

On January 17, 2023, the Mayor and City Council awarded a Contract for the Collins Street Water Main Improvements Project, in the amount of $5,989,498.45, on behalf of Austin Tyler Construction, Inc., based on the Unit Prices provided in their bid.  Change Order No. 1 was approved for a zero-sum value to provide a project time extension.  The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 2, a net decrease in the amount of ($523,574.56) is for the following work:

 

•                     Additional Time Extension to Contract Milestones Due to Delays

o                     IDOT Permit delay

o                     Delay due to Rock Excavation

o                     Railroad Permit Delay

o                     Hills Ave access and coordination delays

•                     Additional Water Main Installation, 6-Inch and 16-Inch

•                     Additional Water Service Line Installation, 1-Inch

•                     Additional Connections to Water Main (Non-Pressure), 6-Inch and 10-Inch

•                     Additional Gate Valve, 6-Inch

•                     Additional Temporary Hot-Mix Asphalt Pavement

•                     Additional Hot Mix Asphalt Pavement Removal and Replacement

•                     Additional Brick Sidewalk Removal and Replacement

•                     Additional Restoration of Lawns and Parkways

•                     Additional Rock Excavation

•                     Additional Detector Loop, Type I

•                     Additional Inlet (Storm Sewer Improvements), Type A, 2' Diameter

•                     Additional Flagging Costs at CN Railroad

•                     Additional time due to unknown water main conflict at 36" Casing Bore at the Railroad Crossing

•                     Additional locating of existing utilities and adjusting of water services / connections at various locations

•                     Addition of Raised Reflective Pavement Markers Per IDOT

•                     Deduct For Unused Pay Items

•                     Balancing Of Contract Value

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($226,357.46)), the Phase IV Lead Service Line Fund (Org 53680000, Object 557200, ($194,128.00)), and the Sewer Improvement Fund (Org 50180020, Object 557200, ($103,089.10)).

 

Also, Pay Estimate No. 8 and Final, in the amount of $1,024,211.90, is presented for approval on behalf of Austin Tyler Construction, Inc.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 2, a net decrease in the amount of ($523,574.56);

 

2.                     Approve Pay Estimate No. 8 and Final, in the amount of $1,024,211.90, on behalf of Austin Tyler Construction, Inc.