Title: Approval of Change Order No. 2 for the Plainfield Road (Theodore St. to Black Rd.) Water Main Improvements Project to Austin Tyler Construction Inc. for a Decreased Amount of ($1,735,236.11) and Pay Estimate No. 11 and Final in the Amount of $564,960.68
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 2 for the Plainfield Road (Theodore St. to Black Rd.) Water Main Improvements Project to Austin Tyler Construction Inc. for a Decreased Amount of ($1,735,236.11) and Pay Estimate No. 11 and Final in the Amount of $564,960.68

end

 

BACKGROUND:

On January 16, 2024, the Mayor and City Council awarded a Contract for the Plainfield Road (Theodore St. to Black Rd.) Water Main Improvements Project, in the amount of $9,475,973.24, on behalf of Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.  Change Order No. 1 was previously approved for a time extension at no cost.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 2 is a final balancing change order with a net decrease in the amount of ($1,735,236.11) for the following work:

 

•                     Balancing of final quantities

•                     Additional Water Main (Open Cut), 6-Inch, Ductile Iron

•                     Additional Water Main (Open Cut), 10-Inch, Ductile Iron

•                     Additional Gate Valve, 8-Inch

•                     Additional Water Service Connection to Water Main and Curb Stop, 1.5-Inch

•                     Additional Water Service Connection to Water Main and Curb Stop, 2-Inch

•                     Additional Water Service Line Type K - Open Cut, 1-Inch

•                     Additional Water Service Line Type K - Open Cut, 1.5-Inch

•                     Additional Water Service Line Type K - Directional Drilling, 2-Inch

•                     Additional Restoration of Lawns and Parkways

•                     Additional HMA Remove and Replace, 2.5-Inch Binder 1.5-Inch Surface

•                     Additional HMA Driveway Remove & Replace, 3-Inch

•                     Additional Detectable Warnings

•                     Additional Temp Pavement Marking

•                     Additional Granular Trench Backfill (Sanitary)

•                     Additional Trench Backfill (Special) (Sanitary)

•                     Additional Sanitary Sewer (Open Cut), 8-Inch, PVC, 0 To 8 Feet Deep

•                     Additional Sanitary Sewer (Open Cut), 15-Inch, PVC, 12 To 15 Feet Deep

•                     Additional Sanitary Service Lines, 6-Inch

•                     Additional Class B Patch (Sanitary)

•                     Deduction for unused quantities

•                     Deduction of lead service line pay items

•                     Deduction Water Main (Open Cut), 8-Inch, Ductile Iron

•                     Deduction Water Main (Open Cut), 12-Inch, Ductile Iron

•                     Deduction Miscellaneous Fittings

•                     Deduction Connect to Water Main (Non-Pressure)

•                     Deduction Gate Valve, 12-Inch

•                     Deduction Valve Vaults

•                     Deduction Fire Hydrant Barrel Extension

•                     Deduction Line Stops

•                     Deduction Sanitary Sewer Removal and Replacement, 8-Inch

•                     Deduction Exploratory Excavation

•                     Deduction Inlet Protection Filter

•                     Deduction Temporary Hot-Mix Asphalt Pavement

•                     Deduction Class B Patch

•                     Deduction HMA Remove & Replace, 10-Inch Binder 2-Inch Surface

•                     Deduction PCC Driveway Removal and Replacement, 6-Inch

•                     Deduction Gravel Driveway Removal and Replacement

•                     Deduction Concrete Curb and Gutter Removal and Replacement

•                     Deduction PCC Sidewalk Removal and Replacement

•                     Deduction Brick Sidewalk Removal and Replacement

•                     Deduction Raised Reflective Pavement Markers

•                     Deduction Epoxy Pavement Markings

•                     Deduction Pavement Marking Removal, Grinding

•                     Deduction Pavement Marking Removal, Water Blasting

•                     Deduction Short Term Pavement Marking Removal

•                     Deduction Temporary Concrete Barrier

•                     Deduction Detector Loop Replacement

•                     Deduction Temporary Traffic Signal Timing

•                     Deduction Tree Root Pruning

•                     Deduction Tree Removal and Replacement

•                     Deduction Rock Excavation

 

In addition, the change order includes a time extension to contract milestones due to field changes and staging for restoration.

 

Funds will be credited to the Water Main Replacement Fund (Org 53880000, Object 557200, ($1,541,615.96)) and the Lead Service Line Replacement Fund Ph 5 (Org 53780000, Object 557200, ($285,806.70)).  Funds will be charged to the Water & Sewer Improvement Fund / Sewer Collection / Construction (Org 50180020, Object 557200, Project Code 24032, $92,186.55).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No.2, for a decreased amount of ($1,735,236.11), to the contract for the Plainfield Road (Theodore St. to Black Rd.) Water Main Improvements Project.

 

2.                     Approve Pay Estimate No. 11 and Final, in the amount of $564,960.68, on behalf of Austin Tyler Construction Inc.

end