TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 4 for the Lead Service Line Replacement Phase 4 Contract to Stip Bros. Excavating, Inc. in the Amount of $500,675.00
end
BACKGROUND:
On February 23, 2023, the Mayor and City Council awarded a contract for the Lead Service Line Replacement Phase 4 project, in the amount of $1,051,700.25, on behalf of Stip Bros. Excavating, Inc., based on the Unit Prices provided in their bid. Subsequently, Change Order No’s 1, 2, and 3 were approved for a net addition of $296,960.00.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 4, a net increase in the amount of $500,675.00, is based on the projected additional quantities of pay items to be installed to complete additional lead service line replacements utilizing existing loan funding from the Illinois Environmental Protection Agency with principal forgiveness. In order to utilize the available funds, the additional lead service line replacement work must be added to an existing contract approved as part of the original loan. Stip Bros. has agreed to maintain their original bid pricing from 2023.
Additional quantities are needed for the following pay items:
• Additional project management
• Additional water service connection to water main - existing
• Additional water service line type K - directional drilling, 1-inch
• Additional water service line type L, 3/4-inch
• Additional water service connection on private property - basement / crawl space
• Additional water meter relocation
• Additional water meter replacement
• Additional hot-mix asphalt removal and replacement, 4" additional binder 2" surface
• Additional hot-mix asphalt driveway removal and replacement, 3-inch
• Additional PCC driveway removal and replacement, 6-inch
• Additional restoration of lawns and parkways
In addition, the change order extends the substantial and final completion dates by 400 days.
Funds are available for this project in the IEPA Loan Fund / Lead Service Line Replacement Phase 4 (Org 53680000, Object 557200, $500,675.00).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 4 to the Lead Service Line Replacement Phase 4 Contract, in the amount of $500,675.00, on behalf of Stip Bros. Excavating, Inc.
end