Legislation Details

File #: 439-26   
Type: Agenda Item Status: Passed
File created: 8/19/2026 In control: City Council Meeting
On agenda: 9/1/2026 Final action: 9/1/2026
Title: Approval of Change Order No. 2 for the Broadway Street (Theodore Street to Ruby Street) Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($1,561,954.91) and Pay Estimate No. 11 and Final in the Amount of $584,633.14
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 2 for the Broadway Street (Theodore Street to Ruby Street) Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($1,561,954.91) and Pay Estimate No. 11 and Final in the Amount of $584,633.14

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the Broadway Street (Theodore Street to Ruby Street) Water Main Improvements Project, in the amount of $10,496,982.64, to Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.  Subsequently, Change Order No. 1 for a time extension at no cost was approved.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 2, a net decrease in the amount of ($1,561,954.91), is a final balancing change order for the following work:

•                     Balancing of final quantities

•                     Deduction for unused quantities

•                     Abandoned gas line removal

•                     Removal of existing unknown structure at Theodore

•                     6" pressure connection at Marble

•                     Unknown sewer repair at Vista

•                     Remove unknown water main at Vista

•                     Remove unknown valve at Ruby

•                     Abandoned gas removal # 2

•                     Unknown water service repair at Ruby

•                     Water main conflict at PQ Corp

•                     Unknown water service at 801 Broadway

•                     Changeable message boards

•                     Ruby street electrical cable repair

•                     Industry Drive cut in tee and valve

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($1,079,517.91)), Lead Service Line Replacement Fund (Org 53880000, Object 557200, ($383,839.50)), and Water & Sewer Improvement Fund / Sewer Collection / Construction (Org 50180020, Object 557200, ($98,597.50), Project 25005).

 

Also, Pay Estimate No. 11 and final in the amount of $584,633.14 is provided for approval.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No.2, for a decreased amount of ($1,561,954.91), to the contract for the Broadway Street (Theodore Street to Ruby Street) Water Main Improvements Project.

 

2.                     Approve Pay Estimate No. 11 and Final, in the amount of $584,633.14, on behalf of Austin Tyler Construction Inc.

end