TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Award of Contract for the Fourth & Eastern Water Main Improvements Project to P.T. Ferro Construction Co. in the Amount of $3,601,647.55

end

 

BACKGROUND:

On January 5, 2021, the Mayor and City Council approved Resolution No. 7613, committing to water conservation through the reduction of non-revenue water in order to comply with the allocation requirements of the Level of Lake Michigan Act, 615 ILCS 50, and the corresponding State regulations.  A condition of the City’s Lake Michigan water allocation permit is completion of the City’s Non-Revenue Water Reduction Plan.  A major component of this Plan is water main replacement.  The water main replacement program, estimated at approximately 3% per year, must be sufficient to achieve the reduction of non-revenue water from the City’s water system to not more than 10 percent by the year 2030.

 

The 2026 Water Main Replacement Program consists of 12 contracts to replace a total of approximately 20 miles of water main, at a cost of approximately $65,760,000.00.  The Fourth & Eastern Water Main Improvements Project was identified to be completed as part of the 2026 program.  This project consists of replacing approximately 7,400 linear feet of water main in various sizes on S Eastern Ave (Osgood St to 5th Ave); Sherman St (Osgood St to 4th Ave); Mound St (Sherman St to Richards St); 3rd Ave (S Eastern Ave to Richards St); Bartleson St (Sherman St to Richards St), and 4th Ave (S Chicago St to Richards St).  Also included in the scope of work for this project is replacement of any lead water service lines encountered.  Attached to this memo is an exhibit showing the project location.

 

Design drawings and bidding documents were prepared and the invitation to bid for the project was advertised in the Joliet Herald-News on Thursday, October 30, 2025.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

On Tuesday, December 2, 2025, at 10:30 a.m., seven (7) sealed bids were received for the Fourth & Eastern Water Main Improvements Project.  The bid summary is as follows:

 

                     CONTRACTOR                     BID AMOUNT

                     P.T. Ferro Construction Co., Joliet, IL                     $3,601,647.55

                     Construction by Camco, Inc., Joliet, IL                     $3,848,583.46

                     Austin Tyler Construction, Inc., Elwood, IL                     $4,010,347.03

                     D Construction Inc., Coal City, IL                     $4,063,235.46

                     Len Cox & Sons Excavating, Crest Hill, IL                     $4,160,829.99

                     M&J Underground Inc., Monee, IL                     $4,447,032.00

                     Airy’s Inc., Joliet, IL                                          $5,048,923.00

                     

                     Engineer’s Estimate                                          $4,560,000.00

 

The low bid from P.T. Ferro Construction Co., in the amount of $3,601,647.55, is 21.02% below the engineer’s estimate.  P.T. Ferro Construction Co. has previously completed similar work for the City and completed this work to the City’s satisfaction.

 

Funds will be charged to the Water Main Replacement Fund (Org 53880000, Object 557200, $3,414,487.55) and Lead Water Service Line Replacement Fund (Org 53880000, Object 557200, $187,160.00).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council award the Contract for the Fourth & Eastern Water Main Improvements Project, in the amount of $3,601,647.55, on behalf of P.T. Ferro Construction Co.