TO: Mayor and City Council
FROM: Gregy Ruddy, Director of Public Works
SUBJECT:
title
Approval of Change Order No. 1 for the 2024 Sidewalk / Curb Replacement Project - Central Joliet on Behalf of D Construction Inc. for Adjustments to the Project Completion Date
end
BACKGROUND:
On August 6, 2024, the Mayor and City Council awarded a Contract for the 2024 Sidewalk / Curb Replacement Project - Central Joliet in the amount of $303,705.00 on behalf of D Construction Inc.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1 provides a time extension for the project completion date due to unanticipated project conditions. There is no cost incurred with this change order. The original completion date was October 30, 2024. The new completion date is June 27, 2025.
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 to the contract for the 2024 Sidewalk / Curb Replacement Project - Central Joliet for an adjustment to the project completion date on behalf of D Construction Inc.