Legislation Details

File #: 440-26   
Type: Agenda Item Status: Passed
File created: 8/19/2026 In control: City Council Meeting
On agenda: 9/1/2026 Final action: 9/1/2026
Title: Approval of Change Order No. 2 for the North Prairie Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($647,156.35) and Pay Estimate No. 8 and Final in the Amount of $418,270.88
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 2 for the North Prairie Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($647,156.35) and Pay Estimate No. 8 and Final in the Amount of $418,270.88

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the North Prairie Water Main Improvements Project, in the amount of $4,792,227.63, to Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.  Subsequently, Change Order No. 1 for a time extension at no cost was approved.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 2, a net decrease in the amount of ($647,156.35), is a final balancing change order for the following work:

•                     Balancing of final quantities

•                     Deduction for unused quantities

•                     Unknown water service repair at Frederick & Ingalls

•                     Existing water main repair at Ingalls & Waverly

•                     Remove abandoned gas main at Ingalls & Prairie

•                     Unknown water service repair at 1112 Fredrick

•                     Remove abandon gas main at Waverly

•                     Unknown water service repair at Hutchins

•                     Disconnect water service at 937 Plainfield Road

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($647,156.35)).

 

Also, Pay Estimate No. 8 and final in the amount of $418,270.88 is provided for approval.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 2, for a decreased amount of ($647,156.35), to the contract for the North Prairie Water Main Improvements.

 

2.                     Approve Pay Estimate No. 8 and Final, in the amount of $418,270.88, on behalf of Austin Tyler Construction Inc.

end