Skip to main content
Joliet City Logo
File #: 6-26   
Type: Consent Agenda Status: Agenda Ready
File created: 12/19/2025 In control: City Council Meeting
On agenda: 1/6/2026 Final action:
Title: Approval of Change Order No. 1 for the 2025-2026 Sidewalk Maintenance Contract to PT Ferro Construction Co. in the Amount of $51,004.14
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Greg Ruddy, Director of Public Works

 

SUBJECT:

title

Approval of Change Order No. 1 for the 2025-2026 Sidewalk Maintenance Contract to PT Ferro Construction Co. in the Amount of $51,004.14

end

 

BACKGROUND:

The City of Joliet Budget allocates funds for sidewalk repair each fiscal year.  The most recent contract for this work was awarded on August 19, 2025.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

The work associated with the 2025 portion of 2025/2026 Sidewalk Contract was completed in November 2025.

 

This change order represents the balancing of the contract quantities from the 2025 portion of the contract.

 

Sufficient funds exist utilizing the Performance Bond Escrow Fund / Infrastructure (Org 32090270, Object 557200, $51,004.14).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 for the 2025-2026 Sidewalk Maintenance Contract to PT Ferro Construction Co. in the Amount of $51,004.14.

end