File #: 22-25    Name:
Type: Consent Agenda Status: Passed
File created: 12/23/2024 In control: City Council Meeting
On agenda: 1/7/2025 Final action: 1/7/2025
Title: Change Order No. 1 for the Hickory Creek East Water Main Improvements Project to Austin Tyler Construction Inc. for a Decreased Amount of ($772,015.73)
Attachments: 1. Approver Report

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Change Order No. 1 for the Hickory Creek East Water Main Improvements Project to Austin Tyler Construction Inc. for a Decreased Amount of ($772,015.73)

end

 

BACKGROUND:

On January 16, 2024, the Mayor and City Council awarded a Contract for the Hickory Creek East Water Main Improvements Project, in the amount of $8,646,715.43, to Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.  The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 1, a net decrease in the amount of ($772,015.73) is for the following work:

 

1)                     Additional water main work due to conflicts

 

2)                     Additional sewer work to extend a sanitary manhole and cap an existing sewer

 

3)                     Balancing of final quantities

 

In addition, Change Order No. 1 includes a time adjustment to the contract milestones for substantial (60 days) and final completion (43 days) due to delays caused by additional work required and completion of punch list items.

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($405,097.72)) and Lead Service Line Replacement Fund Phase V (Org 53780000, Object 557200, ($407,698.66)).  Funds will be charged to the Sewer Collection Fund (Org 50180020, Object 557200, $40,780.65, Project 24033).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 to the contract for the Hickory Creek East Water Main Improvements Project, in the decreased amount of ($772,015.73), on behalf of Austin Tyler Construction Inc.