TO: Mayor and City Council
FROM: Greg Ruddy, Director of Public Works
SUBJECT:
title
Award of Contract for the 2025 City of Joliet Aggregate Materials Price Agreement Contract
end
BACKGROUND:
The 2025 City of Joliet Budget allocated funds to support the maintenance of City roadways, including the purchase of aggregate material. The Aggregate Materials Contract is a part of this maintenance program.
The Public Service Committee will review this matter.
CONCLUSION:
On March 28, 2025, two (2) sealed bids were received for the 2025 City of Joliet Aggregate Contract. The bid summary is as follows:
City of Joliet Aggregate Price Agreement

The proposal explains that the City will complete the hauling of the materials with City-supplied trucks. The City will enter into contracts with the above material suppliers and will purchase materials based on job location (using a haul rate of $0.65 per ton mile), product availability, and what serves the best interest of the City.
It is estimated that approximately 18,500 tons of aggregate will be required for use by the Roadways Division and the Department of Public Utilities.
Sufficient funds exist for the Joliet Aggregate Contracts in the Public Works Roadways Street Repair Materials Fund (Org 09029000, Object 536107, $50,000.00) and the Water & Sewer Operating Fund (Org 50080012, Object 536107, $165,000.00).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council enter into the City of Joliet Aggregate Price Agreement with Holcim and Vulcan at the unit prices noted above.
end