Legislation Details

File #: ID-1611-20   
Type: Change Orders/Pay Estimates /Final Payments Status: Agenda Ready
File created: 2/27/2024 In control: Public Service Committee
On agenda: 3/4/2024 Final action:
Title: Change Order No. 2 for the Lawrence Avenue Lift Station Rehabilitation to J.S. Alberico Construction Co. reducing the contract amount by ($20,250.00) and Final Payment No. 5 in the amount of $102,574.00
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 2 for the Lawrence Avenue Lift Station Rehabilitation to J.S. Alberico Construction Co. reducing the contract amount by ($20,250.00) and Final Payment No. 5 in the amount of $102,574.00

end

 

BACKGROUND:

On June 7, 2022, the Mayor and City Council awarded a Contract for the Lawrence Avenue Lift Station Rehabilitation Project, in the amount of $748,000.00, to J.S. Alberico Construction Co. Inc.  Change Order No. 1 was approved for a net deduction of ($14,760.00).  The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 2, a net decrease in the amount of ($20,250.00), is for the following work:

 

•                     Build and install a new power subpanel to meet additional power requirements.

•                     Deduction of unused contingency allowance.

•                     Deduction of unused integration allowance.

 

Funds will be credited to the Water & Sewer Improvement Fund / Fairmont / Construction (Org 50180370, Object 557200, ($20,250.00)).

 

Also, Payment No. 5 and Final, in the amount of $102,574.00, is presented for approval on behalf of J.S. Alberico Construction Co.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No. 2, a net reduction in the amount of ($20,250.00) to the Lawrence Avenue Lift Station Rehabilitation Project, on behalf of J.S. Alberico Construction Co.

 

2.                     Approve Payment No. 5 and Final, in the amount of $102,574.00, on behalf of J.S. Alberico Construction Co.

end