Title: Approval of Change Order No. 1 for the Marquette Park Water Main Improvements Project to Construction by Camco Inc. for a Deduction in the Amount of ($359,193.74) and Pay Estimate No. 6 and Final in the Amount of $515,575.25
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the Marquette Park Water Main Improvements Project to Construction by Camco Inc. for a Deduction in the Amount of ($359,193.74) and Pay Estimate No. 6 and Final in the Amount of $515,575.25

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a Contract for the Marquette Park Water Main Improvements Project, in the amount of $4,789,334.41, to Construction by Camco Inc., based on the Unit Prices provided in their bid.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

This project has been completed, inspected, and accepted by the Department of Public Utilities.  Change Order No. 1, a net decrease in the amount of ($359,193.74), is the result of:

 

                     Balancing of final quantities

                     Deduction for unused quantities

                     Extra work for 16” x 6” service connection at Queen of Apostle School

                     Extra work for 16” connection at the west limits of the project near Larkin & Campbell

 

Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($359,193.74)).

 

Also, Pay Estimate No. 6 and Final is submitted for payment, in the amount of $515,575.25, on behalf of Construction by Camco Inc.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council take the following actions:

 

1.                     Approve Change Order No.1, for a decreased amount of ($359,193.74), for the Marquette Park Water Main Improvements Project.

 

2.                     Approve Pay Estimate No. 6 and Final, in the amount of $515,575.25, on behalf of Construction by Camco Inc.