TO: Mayor and City Council
FROM: Greg Ruddy, Director of Public Works
SUBJECT:
title
Approval of Change Order No. 1, for the 2024 Resurfacing Contract D to Gallagher Asphalt a Deduction in the Amount of ($328,631.88) and Payment No. 3 & Final in the amount of $113,394.31
end
BACKGROUND:
On Tuesday, November 19, 2024, the Mayor and City Council awarded the 2024 Resurfacing Contract D in the amount of $2,592,888.98 to Gallagher Asphalt.
The Public Service Committee will review this matter.
CONCLUSION:
The project has been completed, inspected and accepted by the Department of Public Works.
Change Order No. 1, a net deduction in the amount of ($328,631.88), is the result of the following:
1. Decrease in paved area (paving limits were reduced).
2. Decrease in quantity of curb replacement.
3. Decrease in required patching area.
4. Balancing of final quantities
Funds are to be reimbursed to the Public Works Capital Improvement Fund / Infrastructure (Org 30090270, Object 557200, ($328,631.88)).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council take the following actions:
1. Approve Change Order No. 1, a net deduction in the amount of ($328,631.88), on behalf of Gallaher Asphalt.
2. Approve Payment No. 3 and Final, in the amount of $113,394.31, on behalf of Gallagher Asphalt.
end