TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 1 for the Cunningham Phase 1 Water Main Improvements Project to Austin Tyler Construction Inc. for a Deduction in the Amount of ($483,877.29)
end
BACKGROUND:
On January 20, 2026, the Mayor and City Council awarded a Contract for the Cunningham Phase 1 Water Main Improvements Project, in the amount of $4,256,274.71, on behalf of Austin Tyler Construction Inc., based on the Unit Prices provided in their bid.
The Public Service Committee will review this matter.
CONCLUSION:
This project has been completed, inspected, and accepted by the Department of Public Utilities. Change Order No. 1 is a final balancing change order with a net decrease, in the amount of ($483,877.29), for the following work:
Balancing of final quantities
Deduction for unused quantities
Connect to existing water main (non-pressure), 6-inch
Specialty landscaping restoration at 925 Oakland
Repair unknown 4" water main at Raynor & Ross
Repair sanitary service lateral at Kelly & Moran
Modification of service line to CVS pharmacy
Gas removal in conflict with water main installation
Repair sanitary service lateral at 914 Wilcox
Unknown water main at Ross & Oakland
Repair sanitary service lateral at 916 Raynor
Remobilize to install additional water services
Locate mismarked water service at 808 Vine Street
Locate service line for Cunningham School
Locate service line for 910 Clement
Repair sanitary service lateral at 551 Ross
Funds will be credited for this project to the Water Main Replacement Fund (Org 53880000, Object 557200, ($480,421.44)) and the Water & Sewer Improvement Fund / Sewer Collection (Org 50180020, Object 557200, ($3,455.85)).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1, for a decreased amount of ($483,877.29), for the Cunningham Phase 1 Water Main Improvements Project...
Click here for full text