Legislation Details

File #: 296-26   
Type: Agenda Item Status: Passed
File created: 5/20/2026 In control: City Council Meeting
On agenda: 6/2/2026 Final action: 6/2/2026
Title: Award of Contract for the Southeast Joliet Sanitary District Water System Improvements Project to Austin Tyler Construction Inc. in the Amount of $2,982,535.68
Attachments: 1. Project Location Map, 2. Approver Report
TO: Mayor and City Council

FROM: Allison Swisher, Director of Public Utilities

SUBJECT:
title
Award of Contract for the Southeast Joliet Sanitary District Water System Improvements Project to Austin Tyler Construction Inc. in the Amount of $2,982,535.68
end

BACKGROUND:
The City of Joliet acquired the Southeast Joliet Sanitary District (District) water and sanitary sewer systems on February 1, 2026. The County is providing funding via multiple sources to fund improvements in the District's system. One of these funding sources is grant funds via the American Rescue Plan Act (ARPA). On October 21, 2025, the Mayor and Council approved the Subrecipient Award Agreement for receipt of $4,025,046 in ARPA funds for water system improvements for the Southeast Joliet Sanitary District. On May 5, 2026, the Mayor and Council approved an amendment to this Agreement increasing the ARPA funds for improvements in SEJSD to $4,106,562.10.

One of the projects identified to be constructed utilizing ARPA funds is replacement of sections of water main that are in poor condition. The location and scope of water main replacement is shown on the attached map. The total length of water main to be installed is 7,181 feet, or 1.36 miles.

Design drawings and bidding documents were prepared and the invitation to bid for the project was advertised in the Joliet Herald-News on Thursday, April 30, 2026.

The Public Service Committee will review this matter.

CONCLUSION:
On Tuesday, May 19, 2026, at 10:00 a.m., three (3) sealed bids were received for the Southeast Joliet Sanitary District Water System Improvements Project. Due to the limited amount of project funding, the project bid required that contractors provide a "base bid" for the base scope of work and an "alternate bid" for the base bid plus additional water main replacement work. Based on the pricing received, there are enough grant funds for the alternate bid amount. The bid summary is as follows:
BASE ALTERNATE...