File #: 492-25   
Type: Consent Agenda Status: Agenda Ready
File created: 9/4/2025 In control: City Council Meeting
On agenda: 9/16/2025 Final action:
Title: Approval of Change Order No. 1 for the Eastside WWTP MCC Replacement and Alternative Water Supply Project JOL0801 - SCADA Project to M J Electric LLC in the Amount of $108,433.02
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the Eastside WWTP MCC Replacement and Alternative Water Supply Project JOL0801 - SCADA Project to M J Electric LLC in the Amount of $108,433.02

end

 

BACKGROUND:

On Tuesday, April 2, 2024, the Mayor and City Council awarded a contract to M J Electric LLC, in the amount of $4,480,000.00, for the Eastside WWTP MCC Replacement and Alternative Water Supply Project JOL0801 - SCADA Project.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

During completion of the work for the Eastside WWTP MCC Replacement project the following deviations from the plans were discovered: 1) one of the major junction boxes in the Blower Building basement was found to be corroded beyond reuse, 2) the MCC D needed to be relocated to accommodate hidden conduits not seen during design, 3) additional surface mounted disconnects were installed on the blower building heaters to maintain uniformity and safety compliance, 4) the HVAC and door replacement allowances needed to be adjusted to cover the actual costs of the needed upgrades.  In addition to these work items a path study was completed to evaluate moving the master SCADA panel to the Eastside WWTP, and the completion date of milestone one was adjusted from December 7, 2024, to February 10, 2025 to allow for the time needed to submit the required documents.

 

Funds will be charged to the Water and Sewer Improvement Fund / Eastside WWTP / Construction (Org 50180802, Object 557200, $108,433.02).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1, a net increase in the amount of $108,433.02, for the Eastside WWTP MCC Replacement and Alternative Water Supply Project JOL0801 - SCADA Project to M J Electric LLC.