Title: Change Order No. 2 for the Joliet Ottawa Water Main Improvements Project to Trine Construction Corp in the amount of $117,267.41
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 2 for the Joliet Ottawa Water Main Improvements Project to Trine Construction Corp in the amount of $117,267.41

end

 

BACKGROUND:

On January 17, 2023, the Mayor and City Council awarded a Contract for the Joliet Ottawa Water Main Improvements Project, in the amount of $6,095,346.00, on behalf of Trine Construction Corp., based on the Unit Prices provided in their bid.  Subsequently, Change Order No. 1 was approved for a zero-sum value to provide a project time extension.  The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 2, a net addition in the amount of $117,267.41 is for the following work:

 

                     Additional 8” storm sewer removal and replacement

                     Additional temporary hot mix asphalt pavement

                     Additional dust control

                     Removal of an unknown abandoned 12” steel gas main

                     Additional work to safely install new watermain under unknown electric duct bank

                     Additional work to provide a temporary repair to an existing vaulted sidewalk

                     Remove and replace deteriorated storm sewer to safely install new water main

                     Repair existing street light conduits found to be buried within the HMA pavement

 

Sufficient funds are available for this project in the Water Main Replacement Fund (Org 53880000, Object 557200, $117,267.41).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 2 to the contract for the Joliet Ottawa Water Main Improvements Project, in the amount of $117,267.41, on behalf of Trine Construction Corp.