TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 2 for the Heggie Park Water Main Improvements Project on behalf of P.T. Ferro Construction Co. for a Deduction in the Amount of ($291.17)
end
BACKGROUND:
On January 21, 2025, the Mayor and City Council awarded a Contract for the Heggie Park Water Main Improvements Project, in the amount of $7,895,977.38, on behalf of P.T. Ferro Construction Co., based on the Unit Prices provided in their bid. Change Order No. 1 was previously approved for a time extension at no cost.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 2, a net decrease in the amount of ($291.17), is for cost adjustments for extra work incurred due to unforeseen conditions encountered during the project as well as the deduction for unused quantities of pay items within the unit price contract. The following is a description of the work included within this change order:
* Additional erosion control at Edgehill
* Additional cost to repair water main break at Williamson & Valley
* Additional cost to remove existing 36" casing and 16" watermain at bore pit location
* Additional cost to remove existing 36" casing and 16" watermain at Hacker / Woodruff
* Additional cost to remove & replace 16" storm sewer at Woodruff/Charlesworth
* Additional cost to reinstall San. MH#04 due to invert elevation conflict
* Additional cost to install (2) sanitary service connections on Edgehill
* Additional cost to remove existing unknown foundation at Fairmont Water Treatment Plant
* Additional cost for erosion control at Edgehill on 1/6/26
* Additional cost to add ditch check at Edgehill slope on 1/7/26
* Additional cost to replace 10" storm line on Edgehill on 1/15/26
* Additional cost to relocate existing electric conduit in conflict with check valve
* Additional cost to install silt fence at Water Treatment Plant and Edgehill
* Deduction for unused quan...