Skip to main content
Joliet City Logo
File #: 67-26   
Type: Agenda Item Status: Agenda Ready
File created: 1/7/2026 In control: City Council Meeting
On agenda: 1/20/2026 Final action:
Title: Award of Contract for the Heggie Park Phase 2 Water Main Improvements Project to Construction by Camco Inc. in the Amount of $5,529,188.04
Attachments: 1. 2026 WM Locations (Heggie Park Phase 2), 2. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and City Council

FROM: Allison Swisher, Director of Public Utilities

SUBJECT:
title
Award of Contract for the Heggie Park Phase 2 Water Main Improvements Project to Construction by Camco Inc. in the Amount of $5,529,188.04
end

BACKGROUND:
On January 5, 2021, the Mayor and City Council approved Resolution No. 7613, committing to water conservation through the reduction of non-revenue water in order to comply with the allocation requirements of the Level of Lake Michigan Act, 615 ILCS 50, and the corresponding State regulations. A condition of the City's Lake Michigan water allocation permit is completion of the City's Non-Revenue Water Reduction Plan. A major component of this plan is water main replacement. The water main replacement program, estimated at approximately 3% per year, must be sufficient to achieve the reduction of non-revenue water from the City's water system to not more than 10 percent by the year 2030.

The 2026 Water Main Replacement Program consists of 12 contracts to replace a total of approximately 20 miles of water main, at a cost of approximately $65,760,000.00. The Heggie Park Phase 2 Water Main Improvements Project was identified to be completed as part of the 2026 program. This project consists of replacing approximately 9,800 linear feet of water main in various sizes on Lloyds Ave (Meeker Ave to Chase Ave); Royce Ave (Francis St to Cleveland Ave); and Francis St / Meeker Ave / Chase Ave / Cleveland Ave (Collins St to Henderson Ave). Also included in the scope of work for this project is replacement of any lead water service lines encountered. Attached to this memo is an exhibit showing the project location.

Design drawings and bidding documents were prepared and the invitation to bid for the project was advertised in the Joliet Herald-News on Thursday, November 6, 2025.

The Public Service Committee will review this matter.

CONCLUSION:
On Wednesday, December 10, 2025, at 10:00 a.m., six (6) sealed bids were re...