Skip to main content
Joliet City Logo
File #: ID-1922-20   
Type: Consent Agenda Status: Agenda Ready
File created: 11/21/2024 In control: City Council Meeting
On agenda: 12/2/2024 Final action:
Title: Change Order No. 1 for the Ottawa Street / Joliet Street Streetscape Project to PT Ferro Construction Co. in the Amount of $10,460.07
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 1 for the Ottawa Street / Joliet Street Streetscape Project to PT Ferro Construction Co. in the Amount of $10,460.07

end

 

BACKGROUND:

On September 3, 2024, the Ottawa Street / Joliet Street Streetscape Repair Project was awarded by the Mayor and City Council in the amount or $113,238.36.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 1, a net increase of $10,460.07, is the result of replacing additional sidewalk along Ottawa Street in front of the Joliet Public Library.

 

Sufficient funds exist utilizing the Public Works Capital Improvement Fund / Infrastructure (Org 30090270, Object 557200, $10,406.07).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 in the amount of $10,460.07 on behalf of PT Ferro Construction Co.