TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 1 for the North Downtown Water Main Improvements Project on behalf of D Construction Inc. for Adjustments to Project Completion Dates
end
BACKGROUND:
On January 21, 2025, the Mayor and City Council awarded a Contract for the North Downtown Water Main Improvements Project, in the amount of $7,251,953.29, on behalf of D Construction Inc., based on the Unit Prices provided in their bid.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1 is to provide a time extension for substantial and final completion dates due to railroad permit delays and weather delays. There is no cost incurred with this change order. The original substantial completion date was October 28, 2025, and the final completion date was November 27, 2025. The new substantial completion date is December 15, 2025, and the final completion date is May 8, 2026.
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 to the contract for the North Downtown Water Main Improvements Project for adjustments to project completion dates, on behalf of D Construction Inc.