TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 1 for the Garnsey Park Sanitary Sewer Rehabilitation Program to Hoerr Construction Inc. in the Amount of $299,346.40
end
BACKGROUND:
On February 4, 2025, the Mayor and City Council awarded a contract for the Garnsey Park Sanitary Sewer Rehabilitation Program, in the amount of $3,221,383.00, to Hoerr Construction Inc.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1, a net increase in the amount of $299,346.40, is a result of the following:
• Flat top installations for manholes with oversized block cones
• Partial cone reconstructions for manhole rehabilitation
• Structural coating for structure with severe H2S corrosion near Rock Run Crossings
• 30-inch and 36-inch Cured-in-Place Pipelining for water/sanitary separation issues
• Transition liners for diameter changes in sewers
• Additional lining work for watermain replacement projects that had water/sewer separation issues
• Removal of quantities that will not be used
Funds will be charged to the Water & Sewer Improvement Fund (Org 50180020, Object 577200, Project 24042, $299,346.40).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1, for an increased amount of $299,346.40, for the Garnsey Park Sanitary Sewer Rehabilitation Program on behalf of Hoerr Construction Inc.
end