TO: Mayor and City Council
FROM: Greg Ruddy, Director of Public Works
SUBJECT:
title
Approval of Change Order No. 2 for the 2023 Sidewalk / Curb Replacement Project Contract B to Davis Concrete Construction Co. in the Amount $15,352.92 and Payment Request No. 4 and Final in the Amount of $29,902.37
end
BACKGROUND:
On June 6, 2023, the Mayor and City Council awarded the 2023 Sidewalk / Curb Replacement Project to Davis Concrete Construction Co. in the amount of $281,725.00. Subsequently, the Mayor and City Council approved Change Order Number 1.
The Public Service Committee will review this matter.
CONCLUSION:
This project has been completed, inspected, and accepted. Change Order No. 2, a net addition in the amount of $15,352.92, is the result of installing barrier curb and additional restoration at ADA ramp locations.
Sufficient funds are available using Public Works Engineering / Construction (Org 09029000, Object 524300, $15,352.92).
Additionally, approval is requested for Payment Request No. 4 and Final, in the amount of $29,902.37, on behalf of Davis Concrete Construction Co.
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council take the following action:
1) Approve Change Order No. 1, a net addition in the amount of $15,352.92.
2) Approve Payment Request No. 4 and Final in the amount of $29,902.37 on behalf of Davis Concrete Construction Co.
end