TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 1 for the Fairmont Water and Sewer Extension Project to Steve Spiess Construction Inc. for a Decreased Amount of ($745,046.58)
end
BACKGROUND:
On March 4, 2025, the Mayor and City Council awarded a Contract for the Fairmont Water and Sewer Extension Project, in the amount of $2,055,015.08, to Steve Spiess Construction Inc.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1, a net decrease in the amount of ($745,046.58), is a result of:
• The water and sewer extension work on State Street was removed from the scope of work.
• Pavement patching scope was changed to reconstruction of HMA roadway.
• A non-pressure connection to the existing watermain was changed to a pressure connection due to defective water valves.
• A water valve and box were added for testing purposes.
Funds will be credited for this project to the Water & Sewer Improvement Fund / Engineering Administration / Construction (Org 50180013, Object 557200, ($745,046.58)).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 for the Fairmont Water and Sewer Extension Project, for a decreased amount of ($745,046.58), to Steve Spiess Construction Inc.