TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Resolution Accepting a Grant of Utility Easements from 705 Henry Street for the Washington Street Water Main Improvements Project
end
BACKGROUND:
The Washington Street Water Main Improvements project is planned for construction in 2026. In order to construct a portion of the project on Washington Street just east of Hickory Creek, permanent & temporary utility easements are required from 705 Henry Street.
The Public Service Committee will review this matter.
CONCLUSION:
City Staff have negotiated a permanent & temporary utility easement agreement with the owner of 705 Henry Street. The attached easement agreement with 705 Henry Street will provide access rights and construction of the water main for the Washington Street Water Main Improvement Project. The landowner has accepted the appraised value of $2,000.00 for the easements.
PIN ADDRESS EASEMENT TYPE APPRAISED VALUE
30-07-15-212-003-0000 705 Henry St Permanent & temporary $2,000.00
Funds will be charged to the Water Main Replacement Fund (Org 53880000, Object 557200, $2,000.00).
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve the resolution accepting the grant of utility easements from 705 Henry Street for the Washington Street Water Main Improvements Project.