TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Award of Contract for the York Avenue Water Main Improvements Project to Construction by Camco Inc. in the Amount of $1,005,084.16
end
BACKGROUND:
On January 5, 2021, the Mayor and City Council approved Resolution No. 7613, committing to water conservation through the reduction of non-revenue water in order to comply with the allocation requirements of the Level of Lake Michigan Act, 615 ILCS 50, and the corresponding State regulations. A condition of the City's Lake Michigan water allocation permit is completion of the City's Non-Revenue Water Reduction Plan. A major component of this Plan is water main replacement. The water main replacement program, estimated at approximately 3% per year, must be sufficient to achieve the reduction of non-revenue water from the City's water system to not more than 10 percent by the year 2030.
The 2026 Water Main Replacement Program consists of 12 contracts to replace a total of approximately 20 miles of water main, at a cost of approximately $65,760,000.00. The York Avenue Water Main Improvements Project was identified to be completed as part of the 2026 program. This project consists of replacing approximately 2,700 linear feet of water main in various sizes on York Ave (E Washington St to Osgood St), E Marion St (York Ave to S Eastern Ave); and Lincoln St (S Eastern Ave to Richards St). Also included in the scope of work for this project is replacement of any lead water service lines encountered. Attached to this memo is an exhibit showing the project location.
Design drawings and bidding documents were prepared and the invitation to bid for the project was advertised in the Joliet Herald-News on Thursday, October 30, 2025.
The Public Service Committee will review this matter.
CONCLUSION:
On Wednesday, December 3, 2025, at 10:30 a.m., seven (7) sealed bids were received for the York Avenue Water Main Improvements P...
Click here for full text