Legislation Details

File #: 339-26   
Type: Consent Agenda Status: Agenda Ready
File created: 6/16/2026 In control: City Council Meeting
On agenda: 7/7/2026 Final action:
Title: Approval of Amendment No. 3 to the Phase I, Phase II, and Phase III Professional Engineering Services for the Joliet Centralized Traffic Management System Improvement Project - MFT Section No. 21-00546-00-TL to Iteris Inc. in the Amount of $14,999.24
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Mayor and City Council

FROM: Greg Ruddy, Director of Public Works

SUBJECT:
title
Approval of Amendment No. 3 to the Phase I, Phase II, and Phase III Professional Engineering Services for the Joliet Centralized Traffic Management System Improvement Project - MFT Section No. 21-00546-00-TL to Iteris Inc. in the Amount of $14,999.24
end

BACKGROUND:
On January 4, 2022, the Mayor and City Council approved a Professional Engineering Services contract for the Centralized Traffic Management System (CTMS) Improvement Project - Phase A to Iteris Inc. in an amount not to exceed $364,397.00. Subsequently, the Mayor and City Council have approved Amendment Numbers 1 and 2.

The Public Service Committee will review this matter.

CONCLUSION:
This professional services contract includes Phase I, Phase II and Phase III engineering services to complete the initial project development, the preparation of contract documents for the implementation / construction, as well as construction oversite. Iteris Inc. has completed the initial project development that will be used with all future phases of the project. Iteris Inc. has also prepared the contract documents used to bid and award the construction contract for the CTMS Phase A and Phase B projects and is completing the contract documents for Phase C. The City has updated the scope for Phase C in order to match the available funding that is programmed which resulted in the need for additional services from Iteris. Amendment No. 3, in the amount of $14,999.24 is the value of those additional services.

The Services will be added to the original contract utilizing time and material rates at a total cost not to exceed $14,999.24, resulting in a total contract cost of $711,512.10.

Funding will be charged to the Motor Fuel Tax Funds (Org 20090270, Object 557200, $14,999.24).

RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Amendment No. 3 for the Phase I, Pha...