TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 2 for the Eastside WWTP MCC Replacement and Alternative Water Supply Project JOL-08-01 SCADA Project to M J Electric LLC in the Amount of $670,647.45
end
BACKGROUND:
On Tuesday, April 2, 2024, the Mayor and City Council awarded a contract to M J Electric LLC, in the amount of $4,480,000.00, for the Eastside WWTP MCC Replacement and Alternative Water Supply Project JOL-08-01 SCADA Project. Subsequently, Change Order No. 1 in the amount of $108,433.02 was approved on September 15, 2025.
The Public Service Committee will review this matter.
CONCLUSION:
During completion of the work for the Eastside WWTP MCC Replacement portion of the project the following items were added to the scope of work: the digester building control panel was severely corroded therefore requiring the entire panel be replaced, multiple failed existing conduits were found and replaced during the installation of new wire, access control modifications were performed throughout the plant allowing for each building to be on the City’s access control system, fiber cable was pulled between all remaining out buildings allowing for the City network to be provided for access control, and the remaining device net communication protocol at the Aux Sable WWTP was replaced allowing for the new PLC to communicate with existing equipment.
During completion of the Alternative Water Supply Project JOL-08-01 SCADA portion of the work the following items were added to the scope of work: the water master PLC was relocated to the Eastside WWTP allowing for a more secure and redundant system and the VT SCADA graphics and programming code was revised to allow for the upgraded PLCs to properly communicate
This change order also extends the contract substantial completion date to November 30, 2026 and extends the final completion date to December 31, 2026.
Funds will be charged to t...