TO: Mayor and City Council
FROM: Allison Swisher, Director of Public Utilities
SUBJECT:
title
Approval of Change Order No. 1 for the 2025 Lead Service Line Replacement Project to Brandt Excavating for Project Completion Time Adjustments
end
BACKGROUND:
On January 21, 2025, the Mayor and City Council awarded a contract for the 2025 Lead Service Line Replacement Project, in the amount of $599,333.53, on behalf of Brandt Excavating, based on the Unit Prices provided in their bid.
The Public Service Committee will review this matter.
CONCLUSION:
Change Order No. 1 is to provide a time extension for substantial and final completion dates due to delays in receiving customer responses needed to schedule the work on private property. There is no cost incurred with this change order. The original substantial completion date was April 16, 2026, and the final completion date was April 30, 2026. The new substantial completion date is May 17, 2027, and the final completion date is May 31, 2027.
RECOMMENDATION:
recommendation
Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 to the contract for the 2025 Lead Service Line Replacement Project for project completion time adjustments, on behalf of Brandt Excavating.