Legislation Details

File #: 591-26   
Type: Consent Agenda Status: Agenda Ready
File created: 11/18/2026 In control: City Council Meeting
On agenda: 12/1/2026 Final action:
Title: Approval of Change Order No. 1 for the 2025 Lead Service Line Replacement Project to Brandt Excavating for Project Completion Time Adjustments
Attachments: 1. Approver Report
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Allison Swisher, Director of Public Utilities

 

SUBJECT:

title

Approval of Change Order No. 1 for the 2025 Lead Service Line Replacement Project to Brandt Excavating for Project Completion Time Adjustments

end

 

BACKGROUND:

On January 21, 2025, the Mayor and City Council awarded a contract for the 2025 Lead Service Line Replacement Project, in the amount of $599,333.53, on behalf of Brandt Excavating, based on the Unit Prices provided in their bid.

 

The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 1 is to provide a time extension for substantial and final completion dates due to delays in receiving customer responses needed to schedule the work on private property.  There is no cost incurred with this change order.  The original substantial completion date was April 16, 2026, and the final completion date was April 30, 2026.  The new substantial completion date is May 17, 2027, and the final completion date is May 31, 2027.

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 1 to the contract for the 2025 Lead Service Line Replacement Project for project completion time adjustments, on behalf of Brandt Excavating.

end