Joliet City Logo
File #: ID-1874-20    Name:
Type: Change Orders/Pay Estimates /Final Payments Status: Agenda Ready
File created: 10/7/2024 In control: Public Service Committee
On agenda: 10/15/2024 Final action:
Title: Change Order No. 2 for the Broadway Street (Marion - Jefferson) Roadway Project - MFT Section No. 23-00557-00-FP to PT Ferro Construction Co. in the amount of $14,563.00
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                           Mayor and City Council

 

FROM:                      Beth Beatty, City Manager

 

SUBJECT:

title

Change Order No. 2 for the Broadway Street (Marion - Jefferson) Roadway Project - MFT Section No. 23-00557-00-FP to PT Ferro Construction Co. in the amount of $14,563.00

end

 

BACKGROUND:

On February 6, 2024, the Mayor and City Council awarded a contract for the Broadway Street (Marion - Jefferson) Roadway Improvement Project, in the amount of $1,247,095.87, to PT Ferro Construction Co.  Subsequently, Change Order No. 1 was approved by the Mayor and City Council.  The Public Service Committee will review this matter.

 

CONCLUSION:

Change Order No. 2, an addition in the amount of $14,563.00, is the result of the following items:

 

1.                     Replacing shallow sanitary service lines in conflict with the new watermain installation.

2.                     Replacement of public sidewalk due to watermain service installation.

 

Sufficient funds exist utilizing the Water & Sewer Fund / Water Main Replacement (Org 50180012, Object 557200 $14,563.00).

 

RECOMMENDATION:

recommendation

Based on the above, it is recommended that the Mayor and City Council approve Change Order No. 2 for the Broadway Street (Marion- Jefferson) Roadway Improvement Project - MFT Sect. No. 23-00557-00-FP, in the amount of $14,563.00 on behalf of PT Ferro Construction Co.

end